16.01.2011

Power engineers of Moscow United Electric Grid Company, colleagues from operating companies of JSC “IDGC Holding”, Federal Grid Company of the Unified Energy System (FGC of UES) of Russia and contracting organizations continue to work on routes of PTL 35-110 kV and in distribution grids in order to restore reliable electric power supply of Moscow Region. For January, 15th 794 trees were removed from PTL, 18 supports were replaced, 4.75 km of wire were restored during works on lines of distribution grids.

In the afternoon on January, 16th workforce of 194 teams (943 people) and 239 units of machinery were used during restoration works. Scheduled repair and restoration works on elimination of consequences of technological disturbances in electric grids of JSC “MOESK” will be continued in Moscow Region in order to provide required parameters of reliability in electric power supply of region’s consumers.


Carrying out of scheduled repair arrangements will require to switch out from electric power of consumers in several inhabited communities, particularly:

in the south – in Podolsk district (Sof’yino village, Podosinki village, Yur’jevka village from 09:00 a.m. till 03:00 p.m.), in Ramenskoe district (Nadezhdino, Biserovo, Lesnoe, Yurovo villages from 09:00 a.m. till 05:00 p.m.);

in the west – in Odyntsovo district (Dubki, Krymskoe, Lyakhovo, Trufanovka, Yakshino from 08:00 a.m. till 05:00 p.m.), in Istra district (Glebovo village, Filatovo village, Antonovka village from 08:00 a.m. till 03:00 p.m.), in Ruza district (Gorodische from 08:00 a.m. till 05:00 p.m.);

in the east – in Shatura district (Tupitsyno village, Pershino village, Novoshino village, Gavrino village, Saprino village, Vorovo village, Tyushino village, Gora from 09:30 a.m. till 05:00 p.m.), in Orekhovo-Zuevo district (Maloe Kishnevo village, Bol’shoe Kishnevo village, Yurkino village, Ostrovo village from 09:00 a.m. till 05:00 p.m.).

JSC “MOESK” asks citizens not to worry and keep calm. You can ask interested questions by twenty-four hour multi-line telephone of “Light line” of Moscow United Electric Grid Company 8-800-700-40-70 and by telephones of temporary informational centres, established in districts of electric grids of JSC “MOESK” (see contact information at the Company’s web-page http://www.moesk.ru/press/news/detail.php?ID=13287).