10.09.2010

Under the Investment program, Western Electric Networks, a branch of JSC “MOESK” are completing installation and alignment of the second transformer with 25 MVA capacities at “Karinskaya” 110/6 kV substation located at Odintsovo district, Moscow Region. Previously, a T-1 transformer has been replaced. Over the implemented works, capacity of the substation has grown from 20 MVA to 50 MVA.