10.09.2010

Under the Investment program, Western Electric Networks, a branch of JSC “MOESK” are completing installation and alignment of the second transformer with 25 MVA capacities at “Karinskaya” 110/6 kV substation located at Odintsovo district, Moscow Region. Previously, a T-1 transformer has been replaced. Over the implemented works, capacity of the substation has grown from 20 MVA to 50 MVA.

The Investment program of JSC “MOESK” includes both building of new objects and reconstruction of objects remaining in operation. All implemented events aimed at provision of reliable electric energy supply, are carried out without disconnection of actual consumers.
true