20.01.2011

Power engineers of Joint-Stock Company “Moscow United Electric Grid Company”, colleagues from IDGC Holding, OJSC operating companies, FGC UES and contracting organizations carry on works at 35-110 kV electric energy transmission lines and distributive grids to recover reliability of the Moscow Region electric energy supply. Over January the 19th, 1,292 trees were taken away only from electric energy transmission lines under works at distributive grids lines, 81 supports replaced, and 9.03 km of wires recovered.

On the night of 19th-20th January, 89 teams (319 workers) and 92 units of techniques used to work at energy objects of JSC “MOESK”.

On January the 20th, planned works aimed at provision of required regional consumers’ electric energy supply reliability parameters will be carried on in the Moscow Region. Staff consisting of 262 teams (1,208 workers) and 284 units of techniques will be involved in the works. It includes 176 teams from branches of JSC “MOESK”, 11 teams from IDGC Holding, OJSC, and 75 teams from contracting organizations.
true