26.04.2013

Within the framework of the investment program JSC “MOESK” is starting to fulfill the next renovation stage of 110/35/10/6 kV substation “Kubinka” located in Odintsovo district of Moscow region.

Earlier the specialists of the Western Electric Grids – branch of JSC “MOESK” installed here the new cells for four sections of 10 kV indoor switchgear.
For the time being, the works are being carried out in commissioning of two power transformers with the capacity of 25 MVA, equipped by a microprocessor unit for the automatic support of the output voltage within the prescribed limits.

Reconstruction of 110 kV outdoor switchgear is planned with the installation of SF6 circuit breakers, which are distinguished by a high reliability, useful life, simple design and safe use.

As a result of the works carried out, the total transformer capacity of the substation will be increased by 1.5 times, which will increase significantly the consumers’ power supply reliability and quality of the Western Moscow region.
true