JSC “Moscow United Electric Grid Company” implemented technological connection of 17,787 consumers in Moscow and the Moscow Area to electric grids for the total power of 991.07 MW (megawatt) in 2010.
The company concluded 34,610 technological connection agreements for the total power of 1,823.8 MW. They include 5,672 agreements in Moscow for the total power of 332.7 MW and 28,938 agreements in the Moscow Area for the total power of 1,491.1 MW.
The majority of all applications for technological connection were accepted by Northern Electric Grids – the branch of JSC MOESK. These are 11,425 applications for the total power of 322.3 MW. They include 95.7% (10,937 pieces for the power of 18,823 MW) - applications of individuals and preferential categories of consumers. The same branch concluded the largest quantity of agreements – 9,686 pieces - for the power of 201.2 MW, and also the largest (as regards the branches of JSC “MOESK”) quantity of technological connections to electric grids – 3,719 pieces for the total power of 105.8 MW.
JSC “MOESK” builds and reconstructs tens of feeding centers, hundreds of kilometers of distribution grids in order to perform technological connection of consumers of Moscow and the Moscow Area. Since 2005, the Company has invested more than RUR 130 billion in development of the electric grid facilities of Moscow and the Moscow Area. The investment program for technological connection for the five year period (2011-2015) is estimated in RUR 115 billion, including RUR 32 billion of charges for distribution grids (the voltage is 0.4 kV, 6 kV and 10 kV).
JSC “MOESK” is the client-focused company which aims to make cooperation with it as comfortable as possible. Its employees do their best so that to make the client be sure of reliability of the Company, its trustworthiness and high quality of performed works already at the stage of signing the agreement.
The “uniform windows” for servicing clients operate in the territory of the Moscow Area in each branch of the Company. The procedures of consideration of applications are as simple as possible, and the control over performance of obligations in respect of technological connection to electric grids of JSC “MOESK” of the representatives of small business and individuals has been strengthened. The electronic system of registering and processing applications for technological connection has been improved, the system application tracking by the client via the company website www.moesk.ru is planned to be implemented in the near future.
Since 26 April 2010, the service center of Moscow Cable Grids – the branch of JSC “MOESK” performing the role of the “uniform window” in the territory of Moscow, has started operations at a new address: Moscow, Alexandra Solzhenitsyna Street, 7. It is located 150 meters away from the underground station “Marxistskaya”.
The Internet Reception of General Director of JSC “Moscow United Electric Grid Company” functions on the official website of the Company since February 2009 to establish the effective feedback between the consumers of the services of JSC “MOESK” and its management. The Company clients may turn to General Director with a question, proposal in respect of improvement of the activity or complaint. This may be done by way of filling in the established form on the website www.moesk.ru on the page of the Internet Reception and sending the electronic mail.
Besides, the round-the-clock “Light Line” operates in JSC “MOESK”. Electricity consumers of Moscow and the Moscow Area may address in respect of technological breaks and faults in electricity supply using the uniform free-of-charge telephone number 8-800-700-40-70. If electricity outage is observed in a house, apartment or office, just dial this number and operators will give the comprehensive information on the reason of absence of electricity and specify the provisional time of voltage supply.
The main shareholders of JSC “MOESK” are IDGC Holding, OJSC (51%), Group of Companies “Gazprom” (31%) and Group of Companies of the Moscow Government (8%), more than 8% are in free float.
The structure of the company includes more than 607 high-voltage feeding centers of 35/110/220 kV voltage and the total power of 43,713 MVA. The total length of 35-220 kV power lines is 15,590 km; 35-110-220-500 kV high-voltage cable lines – 1,408 km, the total length of distribution electric grids is 121,145 km. The total of distribution and transformer substations exceeds 30 thousand pieces. The number of the personnel is 15,755 people.
The round-the-clock “Light Line” operates in JSC “MOESK”. Now electricity consumers of Moscow and the Moscow Area can address in respect of technological breaks and faults in electricity supply using the uniform free-of-charge telephone number 8-800-700-40-70!
The labor team of the companies of IDGC Holding exceeds 190 thousand qualified specialists. Moscow United Electric Grid Company attending the overwhelming number of the consumers of Moscow and the Moscow Area employs 15,755 people.
The main shareholders of JSC “MOESK” are IDGC Holding, OJSC (51%), Group of Companies “Gazprom” (31%) and Group of Companies of the Moscow Government (8%), more than 8% are in free float.
The structure of the company includes more than 607 high-voltage feeding centers of 35/110/220 kV voltage and the total power of 43,713 MVA. The total length of 35-220 kV power lines is 15,590 km; 35-110-220-500 kV high-voltage cable lines – 1,408 km, the total length of distribution electric grids is 121,145 km. The total of distribution and transformer substations exceeds 30 thousand pieces.
The primary goals of development of JSC “MOESK”, the other 12 IDGCs/DGCs and the management company of the Holding on behalf of IDGC Holding, OJSC is maintenance of reliable, uninterrupted and qualitative supply of electricity to consumers, technological connection of electricity consumers, and improvement of investment appeal of distribution electric grid assets.
The company concluded 34,610 technological connection agreements for the total power of 1,823.8 MW. They include 5,672 agreements in Moscow for the total power of 332.7 MW and 28,938 agreements in the Moscow Area for the total power of 1,491.1 MW.
The majority of all applications for technological connection were accepted by Northern Electric Grids – the branch of JSC MOESK. These are 11,425 applications for the total power of 322.3 MW. They include 95.7% (10,937 pieces for the power of 18,823 MW) - applications of individuals and preferential categories of consumers. The same branch concluded the largest quantity of agreements – 9,686 pieces - for the power of 201.2 MW, and also the largest (as regards the branches of JSC “MOESK”) quantity of technological connections to electric grids – 3,719 pieces for the total power of 105.8 MW.
JSC “MOESK” builds and reconstructs tens of feeding centers, hundreds of kilometers of distribution grids in order to perform technological connection of consumers of Moscow and the Moscow Area. Since 2005, the Company has invested more than RUR 130 billion in development of the electric grid facilities of Moscow and the Moscow Area. The investment program for technological connection for the five year period (2011-2015) is estimated in RUR 115 billion, including RUR 32 billion of charges for distribution grids (the voltage is 0.4 kV, 6 kV and 10 kV).
JSC “MOESK” is the client-focused company which aims to make cooperation with it as comfortable as possible. Its employees do their best so that to make the client be sure of reliability of the Company, its trustworthiness and high quality of performed works already at the stage of signing the agreement.
The “uniform windows” for servicing clients operate in the territory of the Moscow Area in each branch of the Company. The procedures of consideration of applications are as simple as possible, and the control over performance of obligations in respect of technological connection to electric grids of JSC “MOESK” of the representatives of small business and individuals has been strengthened. The electronic system of registering and processing applications for technological connection has been improved, the system application tracking by the client via the company website www.moesk.ru is planned to be implemented in the near future.
Since 26 April 2010, the service center of Moscow Cable Grids – the branch of JSC “MOESK” performing the role of the “uniform window” in the territory of Moscow, has started operations at a new address: Moscow, Alexandra Solzhenitsyna Street, 7. It is located 150 meters away from the underground station “Marxistskaya”.
The Internet Reception of General Director of JSC “Moscow United Electric Grid Company” functions on the official website of the Company since February 2009 to establish the effective feedback between the consumers of the services of JSC “MOESK” and its management. The Company clients may turn to General Director with a question, proposal in respect of improvement of the activity or complaint. This may be done by way of filling in the established form on the website www.moesk.ru on the page of the Internet Reception and sending the electronic mail.
Besides, the round-the-clock “Light Line” operates in JSC “MOESK”. Electricity consumers of Moscow and the Moscow Area may address in respect of technological breaks and faults in electricity supply using the uniform free-of-charge telephone number 8-800-700-40-70. If electricity outage is observed in a house, apartment or office, just dial this number and operators will give the comprehensive information on the reason of absence of electricity and specify the provisional time of voltage supply.
*****
JSC “Moscow United Electric Grid Company” is the largest Interregional Distribution Grid Company of Russia. JSC “MOESK” attends the consumers of Moscow and the Moscow Area. The main kinds of activity are rendering of electricity transportation services to consumers and technological connection to electric grids.
The main shareholders of JSC “MOESK” are IDGC Holding, OJSC (51%), Group of Companies “Gazprom” (31%) and Group of Companies of the Moscow Government (8%), more than 8% are in free float.
The structure of the company includes more than 607 high-voltage feeding centers of 35/110/220 kV voltage and the total power of 43,713 MVA. The total length of 35-220 kV power lines is 15,590 km; 35-110-220-500 kV high-voltage cable lines – 1,408 km, the total length of distribution electric grids is 121,145 km. The total of distribution and transformer substations exceeds 30 thousand pieces. The number of the personnel is 15,755 people.
The round-the-clock “Light Line” operates in JSC “MOESK”. Now electricity consumers of Moscow and the Moscow Area can address in respect of technological breaks and faults in electricity supply using the uniform free-of-charge telephone number 8-800-700-40-70!
*****
JSC “Moscow United Electric Grid Company” (JSC “MOESK”) is Russia’s largest regional distribution grid company (DGC), the controlling interest in which (51%) is owned by Interregional Distribution Grid Companies Holding, OJSC (IDGC Holding, OJSC), which carries out management by IDGCs/DGCs using corporate methods (through the Boards of Directors). More than 330 thousand of shareholders hold the shares in IDGC Holding, OJSC. The supervising shareholder is the state owning 53% of shares.
The labor team of the companies of IDGC Holding exceeds 190 thousand qualified specialists. Moscow United Electric Grid Company attending the overwhelming number of the consumers of Moscow and the Moscow Area employs 15,755 people.
The main shareholders of JSC “MOESK” are IDGC Holding, OJSC (51%), Group of Companies “Gazprom” (31%) and Group of Companies of the Moscow Government (8%), more than 8% are in free float.
The structure of the company includes more than 607 high-voltage feeding centers of 35/110/220 kV voltage and the total power of 43,713 MVA. The total length of 35-220 kV power lines is 15,590 km; 35-110-220-500 kV high-voltage cable lines – 1,408 km, the total length of distribution electric grids is 121,145 km. The total of distribution and transformer substations exceeds 30 thousand pieces.
The primary goals of development of JSC “MOESK”, the other 12 IDGCs/DGCs and the management company of the Holding on behalf of IDGC Holding, OJSC is maintenance of reliable, uninterrupted and qualitative supply of electricity to consumers, technological connection of electricity consumers, and improvement of investment appeal of distribution electric grid assets.