29.08.2013

Detailed information about the actual reserve of the capacity at each substation of JSC “MOESK” is placed on the Company’s webpage.

In order to learn on one’s own about a possibility of the technological connection to the electric grids of JSC “MOESK”, the customers should just address to the technological connection portal, where the “Map of the feeding centers of the load” is effective.

Section “Regions accessible for connection of large consumers” represents a list of the substations (SS), the construction or reconstruction whereof will make it possible to make a technological connection of applicants, who wish to connect the capacity of over 50 megawatt. Currently there are 7 such feeding centers in the Moscow Region territory.

Currently the reserve of capacity (with due account for the concluded technological connection contracts) is available at 271 substations (SS) and amounts to 3,616.28 megavolt-ampere (MVA), including: 54 feeding centers and 1,464.76 MVA in the territory of Moscow (in the new boundaries) and 217 SS and 2,151.52 MVA in the Moscow Region territory.

The biggest reserve of capacity is available in the South-Eastern, South-Western, Southern, Zelenogradskiy, Northern and Western administrative districts of Moscow.

In the Moscow Region territory the following regions are mostly provided with the reserve energy capacities: Krasnogorskiy, Mytischinskiy, Noginskiy, Istrinskiy municipal regions, as well as city district Khimki.

On the same portal, in section “Marketing researches”, large consumers (who wish to connect the capacity of over 670 kW) are offered to inform MOESK about their own development plans from the point of view of the technological connection necessity of the new facilities in the short-term and long-term view.

“This information is very important for us, – told acting Deputy Director General for the technological connection and services development Alexander Pyatigor. – Using it, MOESK forms its own Investment program, participates in elaboration of the perspective development schemes of the electric grids of Moscow and Moscow Region, which finally, will make it possible to provide a reliable, cost effective and timely power supply of the new consumers”.