The branch of JSC "Moscow United Electric Grid Company" - Moscow Cable Grids (MCG) carried out works related with power supply of the 1st stage of residential development in Lyubertsy fields of aeration – micro districts 8 and 12A.
Works on grid connection of new micro districts to electric grids of MOESK are held within the framework of the targeted investment program of the city of Moscow, as well as grid connection agreements concluded with the grid company.
Energy specialists of MCG have laid over 10 km of 10 kV cable lines, installed and energized six transformer substations with total combined capacity of 8.9 MW. The total costs of the project will exceed RUR 40 million.
According to Nikolay Kkarpukhin, deputy director of the branch for capital construction, all works at the facility are carried out in strict accordance with the agreed schedules in constant cooperation with the Construction Department of of Moscow, developers and other interested organizations.