10.07.2013

013.jpgBased on the results of the first half of the year, the branch of JSC "MOESK" - Western Electric Grids invested RUR 1.7 billion in construction, renovation and reconstruction. For the period from January to June, more than 480 km of lines of different voltage classes and nearby 80 MVA of transformer capacity were commissioned in total.

Todate, large-scale reconstruction of 110 kV substations (S) "Odintsovo", "Naro-Fominsk", "Pernatovo" is held. This year it is planned to hold survey work and further renovation of 110 kV feeding centers "Solov’yevo", "Dar’yino", "Volokolamsk", "Mozhaisk", "Zvenigorod".

014.jpgIn addition, for transit of capacity from 750 kV "Gribovo" S, energy specialists will perform rearrangement of existing 110 kV overhead lines: "Gribovo - Lotoshino", "Gribovo - Gazovaya", "Gribovo - Shahovskaya".

According to Viktor Ivanov, director of the Western Electric Grids, renovation of power facilities and reconstruction of existing grids is carried out to meet the growing needs and interests of the region. In the course of implementation of the investment program, the Western Electric Grids apply modern technologies, materials and equipment, so that the required amount of work is carried out efficiently and in short time.

Let us remind you that the branch plans to invest RUR 3.5 billion in development of the western Moscow Area in 2013. In such a manner, the energy specialists of JSC "MOESK" ensure power supply of high quality and make a significant contribution to development of the infrastructure of the Moscow Region.